Information concerning works on the basins of the Pont Peyrin zone

As part of the extension of the Pont Peyrin activity zone and in order to manage the problems linked to periodic floods, work will be carried out on rainwater retention basins from 29 September until the end of the year.

This project will involve two complete road cuts according to the following dates and provisions:

– Rue Colette Besson, between the roundabout of the RD 634 and the delivery access of “Bricomarch√©”: from Monday 10 October 07 h 00 to Friday 22 October 17 h 00.

– RD 634, between the “L’Isle-Jourdain” roundabout and the access to the “retail park” shops: from Monday 25 October 07 h 00 to Friday 05 November 17 h 00.